2023
Laying of the First Stone of the "Graha Kasih" Building
The groundbreaking was held on July 7 2023. It was
attended by several government agencies and religious,
social and security services, TNI Polri and their
ranks. This development already has official and legal
permission in writing, stamped with SK number
601/0340/B-11/IMB/VI/2021. Decree date June 14 2021.
For 2 years, there have been pros and cons to this
development plan, so this development plan has been
pending, but we are grateful that this is God's
perfect timing.
Building Deconstruction Process
Demolition of residential buildings to level the land
and start construction of new buildings with new
permits.
Footplate Foundation Construction Process
The work has reached the foundation excavation,
excavation of hearths, concrete rebates, footplate
formwork and installation of footplates at
predetermined points. Previously there was leveling of
the excavated land and electrical arrangements for
supporting equipment.
Pillar Construction
Pillar foundation cast construction completes the
construction of the footplate and building foundation
structure, in the future we will continue with the
next floor casting.
2nd Floor Concrete Construction
Installation of scaffolding for 2nd floor cast
concrete begins. Casting work will be carried out with
ready mix carried out next week.
2nd Floor Casting Process
This week, casting was carried out for the foundation
of the 2nd floor. Thank God, we were able to carry out
this casting process well and smoothly.
Pillar Construction Process, 3rd floor
Construction of the 3rd floor Pillar has started, work
will take place in a few days and next month it is
likely that the casting work will be carried out on
the 3rd floor.
3rd Floor Casting Process
The process of making pillars and scaffolding frames
for the 3rd floor foundation has been completed. Next
week, it is planned that casting will be carried out
on the 3rd floor of the Graha Kasih C3 Efata building.
2024
Painting of the new building.
This process involves painting the new building both
inside and outside.
Network installation process and finishing
installation of dim light points and air conditioning,
and network installation process.
Creation of a plaque.
Planning an inauguration with the creation of a plaque
to be signed by the Mayor of Solo.
Inauguration of the new building.
This inauguration was attended by several honored
guests, government agencies, representatives of
religious organizations, FKUB representatives, and
BAGS, and was attended by the Deputy Mayor of
Surakarta.