Menu

2023

July 07, 2023

Laying of the First Stone of the "Graha Kasih" Building

The groundbreaking was held on July 7 2023. It was attended by several government agencies and religious, social and security services, TNI Polri and their ranks. This development already has official and legal permission in writing, stamped with SK number 601/0340/B-11/IMB/VI/2021. Decree date June 14 2021. For 2 years, there have been pros and cons to this development plan, so this development plan has been pending, but we are grateful that this is God's perfect timing.

July 10, 2023

Building Deconstruction Process

Demolition of residential buildings to level the land and start construction of new buildings with new permits.

August 21, 2023

Footplate Foundation Construction Process

The work has reached the foundation excavation, excavation of hearths, concrete rebates, footplate formwork and installation of footplates at predetermined points. Previously there was leveling of the excavated land and electrical arrangements for supporting equipment.

Sept 17, 2023

Pillar Construction

Pillar foundation cast construction completes the construction of the footplate and building foundation structure, in the future we will continue with the next floor casting.

Sept 28, 2023

2nd Floor Concrete Construction

Installation of scaffolding for 2nd floor cast concrete begins. Casting work will be carried out with ready mix carried out next week.

Oct 10, 2023

2nd Floor Casting Process

This week, casting was carried out for the foundation of the 2nd floor. Thank God, we were able to carry out this casting process well and smoothly.

Oct 18, 2023

Pillar Construction Process, 3rd floor

Construction of the 3rd floor Pillar has started, work will take place in a few days and next month it is likely that the casting work will be carried out on the 3rd floor.

Nov 11, 2023

3rd Floor Casting Process

The process of making pillars and scaffolding frames for the 3rd floor foundation has been completed. Next week, it is planned that casting will be carried out on the 3rd floor of the Graha Kasih C3 Efata building.

2024

March 29, 2024

Painting of the new building.

This process involves painting the new building both inside and outside.

April 6, 2024

Network installation process and finishing

installation of dim light points and air conditioning, and network installation process.

April 27, 2024

Creation of a plaque.

Planning an inauguration with the creation of a plaque to be signed by the Mayor of Solo.

Mei 31, 2024

Inauguration of the new building.

This inauguration was attended by several honored guests, government agencies, representatives of religious organizations, FKUB representatives, and BAGS, and was attended by the Deputy Mayor of Surakarta.

Thank you to everyone who participated in the event and the inauguration of our new church building. God bless.